95. In addition to the general content prescribed by section 16, every application for authorization for an activity referred to in this Chapter must include the plans and specifications for the facilities concerned.
For the construction, relocation or operation of an electric power control or transformer station or an electricity storage system with a voltage equal to or exceeding 120 kV, the application for authorization must include a predictive noise study when a dwelling or public institution is located less than 600 m from the site of the activities.
For a power station burning fossil fuels, the application for authorization must include air dispersion modelling in accordance with the requirements of Schedule H of the Clean Air Regulation (chapter Q-2, r. 4.1).
O.C. 871-2020, s. 95.
In force: 2020-12-31
95. In addition to the general content prescribed by section 16, every application for authorization for an activity referred to in this Chapter must include the plans and specifications for the facilities concerned.
For the construction, relocation or operation of an electric power control or transformer station or an electricity storage system with a voltage equal to or exceeding 120 kV, the application for authorization must include a predictive noise study when a dwelling or public institution is located less than 600 m from the site of the activities.
For a power station burning fossil fuels, the application for authorization must include air dispersion modelling in accordance with the requirements of Schedule H of the Clean Air Regulation (chapter Q-2, r. 4.1).
O.C. 871-2020, s. 95.